Power Distribution Upgrades, Romberg Tiburon Center

Project Owner

The California State University

Project Location

Tiburon, California

Project Value

$1.3m

Project Description

This project removed the old, deteriorated overhead 12kV campus power distribution system and replaced it with a new 12kV underground service. A 250kW emergency generator, 500 kVA transformer, automatic transfer switch and electrical vaults were provided and installed to service the main classroom and laboratory building in the event of a power outage.